What a Crane Quotation Must Define

A crane quotation is a statement of the equipment and services offered for a stated lifting duty, with the price and the responsibilities of the maker and purchaser set out before an order is placed. The quotation is the basis of the eventual contract, usually the purchaser's order, and therefore its scope, terms and technical requirements must be mutually understood and agreed.

MG Type Double Girder Gantry Crane3

Define the Duty in a Crane Quotation

Crane Duty and Working Conditions

The crane must be adequate for its intended job. The maker needs to know the range of loads, number of lifts and hours worked. The purchaser may not know the class definitions, and if in doubt should seek the maker's advice. Light or intermittent duties, e.g. infrequent lifting in a machine shop, would justify a lower class than continuous working in a steel stock or container yard.

Span, Lift Height and Building Clearance

Span is the distance between the crane rail centrelines. It must be measured accurately on site, particularly if secondhand or existing tracks are used. On no account should a crane be ordered without the span having been checked by the purchaser or by the maker's representative. Spans should be given in millimetres.

Equipment and Interfaces in a Crane Quotation

Hoist and Controls in a Crane Quotation

Standard single speed hoists have one lifting speed and one lowering speed. Where loads are delicate or accurately positioned, the maker may offer a micro-speed for the hoist.

Runway Rails and Wheel Loads

The runway may be supplied by the purchaser, to carry the crane rails. The crane quotation should state the maker's requirements for the runway, e.g. rail size, rail fixing, rail level tolerance, and the maximum wheel loads to be imposed. The maximum wheel loads, not the average, should be given, since these determine the strength of the runway beams and the size of the columns. The crane quotation should state whether the crane is to be supplied with its own rails (some makers do, some do not), together with the crane buffer and rail-stop details. The quotation should also state the clearance required beyond the rail centres; the overall width of the crane, including any platform or walkway, must be clearly shown.

Power Supply and Site Wiring

The crane maker needs to know the supply characteristics, i.e. voltage, frequency. The purchaser should state the maximum and minimum voltages that can occur, since low voltage can cause overheating in motors and contactor chattering or failure. It may be necessary to specify the tappings on the crane transformer if the crane is to operate normally at the lowest voltage, and the purchaser should state where the crane isolator is to be located.

Costs Outside the Crane Quotation

Freight, Incoterms and Unloading

The purchaser must state the delivery point, particularly if it is not at rail or road side. The quotation should state whether carriage is included and how the crane will be packed. Export orders need seaworthy packing, and for all orders the maker should state whether the packing is returnable or expendable. The maker should also tell the purchaser the weights and dimensions of the largest packages and any exceptionally heavy items, so that the purchaser can arrange off-loading and transport from the port or station to the site.

Installation, Commissioning and Load Testing

The quotation should state whether erection is included, and the conditions; the crane maker should visit the site before quoting, to see if the building is ready to receive the crane. Rail level tolerances, and the absence of scaffolding or other restrictions must be checked. The purchaser is usually responsible for providing power and water on site, and light and heating for the maker's erectors.

MH Type Single Girder Gantry Crane3

Drawings, Spare Parts and Warranty

The purchaser should state how many copies of drawings and maintenance manuals are required, and whether approval of the drawings is required before manufacture. The maker's quotation should state the time needed for the drawings to be approved and the time needed for manufacture after the approved drawings are returned. The purchaser should state if the crane is to be paid for on delivery and if the crane is to be held in storage, and at whose risk.

Resolve Crane Quotation Gaps Before Ordering

Crane Quotation Checklist

The following particulars should be settled between the purchaser and the crane maker before an order is placed:

(a) the duty;

(b) the span and the headroom;

(c) the maximum and minimum hoist speeds; the number of speeds, and whether micro-speed is required;

(d) the electrical supply;

(e) the runway and rails;

(f) whether the maker or the purchaser is to provide the runway, the rail stops, the crane rails and the current collector system;

About FLAGCRANE

FLAGCRANE designs, manufactures, installs and services cranes. Our published HD overhead crane and MH gantry crane ranges have different duty classes, so a quotation should identify the model and configuration selected for the site. Application drawings and operating requirements may be sent to FLAGCRANE for an itemized offer.

QDX Type Double Beam Electric Overhead Crane with Trolley3

FAQ

Q: What should an overhead crane quotation include?

A: The offer should identify the crane selected for the duty stated in the enquiry. Capacity, span, lifting height, hoist speeds and controls have to be read with the drawing. The purchaser should also find a written division of responsibility for the runway, electrical supply, carriage, erection and testing.

Q: Does a crane quotation include installation and commissioning?

A: It may do so, but the equipment price by itself gives no answer. The erection clause should state the work included and the conditions at the site. The purchaser must establish who provides installers, access equipment, power for commissioning, test weights and the documents needed for acceptance.

Q: Are runway rails and power systems included in an overhead crane quotation?

A: The rails, fixings and current collectors should be named in the schedule, whether they are supplied by the maker or by the purchaser. The electrical connection point is another boundary to settle. The maker's wheel-load and supply information will be needed by those preparing the runway and incoming feed.

Q: What does "by others" mean in a crane quotation?

A: It excludes an item from the maker's stated scope, leaving its provision to the purchaser or another contractor. The wording is incomplete unless the responsible party and point of handover are recorded. The cost of that work belongs in the comparison of offers, even though it is absent from the maker's price.

Q: What should a steel-mill crane quotation say about operating conditions?

A: The purchaser should give the range of loads, number of lifts and hours worked, together with heat, dust and the nature of the material handled. The maker can then state the duty proposed. A crane intended to handle molten metal requires a separate technical review of the application and proposed equipment.